The equipment inspection of water treatment equipment plant is an important system to grasp the operation status of the equipment, so as to timely discover hidden dangers, check the dynamic operation of the equipment, and ensure the operation of the equipment ******. It is carried out seriously according to the prescribed route. Normal inspection should be conducted every 2 hours. (Night shift usually uses off light inspection).

Normal inspection of water treatment equipment factory, inspection content:

1) Check if the oil level of the oil injection equipment (including the pipe sleeve and main body) is normal, the oil color should be transparent and not black, and the shell should have no leakage or oil leakage.

2) The flexible wire has no loose, broken, overly tight, loose or other phenomena, and the contact of the switch blade and the joint do not generate heat.

3) The surface of porcelain materials such as porcelain bottles and porcelain sleeves is clean, without any damage, cracks, discharge flashover, and severe corona.

4) The sound and temperature of transformers, inverters, voltage transformers, reactors, etc. are normal. The explosion-proof film is intact.

5) The opening and closing indication position of the oil switch is correct. There is no abnormal sound inside the switch, and there is no oil spray on the explosion-proof tube. The operation box door and the high-voltage switchgear network door are tightly closed.

6) The lightning arrester and grounding device (including recorder) are intact and in good condition.

7) The outer shell of the power capacitor is not deformed, there is no abnormal sound inside, and all connections are in good condition.

8) There is no oil leakage or discharge in the power cable terminal box, and there is no bulging or overflow of asphalt.

9) Whether the relay protection device operates normally, whether the contact position is correct, whether the wiring terminals are burnt red or broken, whether the pressing plate position is consistent with the required position, and whether the indicating position of the indicator light is correct.

10) Whether the position of the relay and automatic device is consistent and whether the contact is good.

11) Check for any abnormal sounds, sparks, or burnt odors in the relay and secondary wiring.

Inspection system for water treatment equipment plant:

a. The pool surface inspection work is uninterrupted, and the entire factory equipment is inspected every 2 hours. The meal time is coordinated to be on duty;

b. Timely record and report abnormal situations;

c. When the water quality of the biochemical pool is abnormal, investigate the responsibility of the on duty patrol personnel 4 hours ago;

d. Follow the guidance and scheduling of process scheduling personnel.


专业水处理的疑难问题,产品选型问题,可以单击下面的微信二维码电话联系贺工在线指导,长按微信二维码可自动识别添加贺工微信沟通解决您的疑难问题

佳洁纯水资深技术贺工
Buy antifreeze production equipment, don't be tempted by sma
Previous 2024年04月15日
Why are more and more food processing plants using pure wate
Next 2024年04月15日

相关推荐